Staircase Pressurisation Fan Testing and Commissioning
Staircase Pressurisation Fan Testing and Commissioning
Ensure that the pressurization fan installation is complete and mechanical completion is approved.
Ensure that vibration isolators are complete with proper alignment of fan.
Ensure that no damage occurs between mechanical completion and pre commissioning.
Ensure that orientation of the fans is as per approved shop drawings.
Repair all damages to the equipment finish paint if any.
Check the…
View On WordPress
0 notes
Text
Sanitary Ware Testing
Ensure that the Sanitary wares installation is completed and mechanical completion is approved
Ensure that no damage occurs between mechanical completion and pre commissioning.
Check the sanitary wares coordinated with architectural design.
Check the wash basin, shower point, WC, Hand spray, paper holder, etc. as per Design location.
Make sure that the Floor drain point is installed and…
View On WordPress
0 notes
Text
RMU Testing
Only authorized personnel will be allowed to enter the sub stations and LV rooms during testing.
The test areas will be demarcated with warning tapes and barriers will be erected to restrict movement of irrelevant personnel
Limited access permit will be issued for the specific test area valid for one day during normal working hours.
The equipment under test will be completely isolated and…
View On WordPress
0 notes
Text
OAHU Commissioning
Ensure that the OAHU is complete and mechanical works completion is approved.
Sealing between the access panels and the frames shall be checked to ensure that there is no leakage of air. Ensure that the AHU chamber is locked and fan outlet is temporary covered with suitable protection.
Repair all damages to the equipment finish paint.
Check OAHU installed as per the approved shop drawings and…
View On WordPress
0 notes
Text
Earth Electrode Resistance Measurement Using Dedicated Earth Electrode Tester
Earth Electrode Resistance Measurement Using Dedicated Earth Electrode Tester
A proprietary Earth Electrode test device should be used.
Auxiliary Earth spikes should be applied at least 15 m apart and 15 m distant from the Earth Electrode under test.
An Earth resistance value of less than 10 ohms is required for a Locally Earthed System.
An additional number of Earth Electrodes may be required (or deeper electrodes) to achieve the required Earth resistance value.
Due…
View On WordPress
0 notes
Text
Light Fixture Testing and Commissioning
Light Fixture Testing and Commissioning
Ensure that the Light Fittings installation is complete and mechanical completion is approved & all comments on the installation ITRs are incorporated.
Ensure that no damage has occurred between mechanical completions & pre-commissioning.
Ensure the installation is in line with the approved False Ceiling layout & manufacturer’s recommendations.
Ensure that all accessories such as lamp, fuses,…
View On WordPress
0 notes
Text
Indoor Lux Level Test
Indoor Lux Level Test
Measurement of lighting levels is a major part of the building commissioning process. Measurement and processing of lux levels need special attention of the commissioning professionals. Sample points of measurement must be clearly defined and marked. Calculation of results must be accurate and interpreted correctly. This section will cover various types of measuring devices, calibration…
View On WordPress
0 notes
Text
IPTV System Commissioning
Verify the physical connectivity by checking LEDs in the servers. All LED should be linking
Check if all equipment installed can be seen
Connect to devices in the assigned VLAN at MDF and at IDF level to verify connectivity
Connect to devices in the room in assigned VLAN to test the connectivity.
Use Video LAN software to test multicasting across network
Check all the channels are present to the…
View On WordPress
0 notes
Text
GRP Water Tank Testing
GRP Water Tank Testing
Ensure that the tanks installation is completed and mechanical works are approved.
Ensure that no damage occurs between mechanical completion and pre commissioning.
Check the tank panel arrangement.
Check that the Relevant Piping is completed with valve accessories.
Make sure that the Gasket is properly fixed for all the Tanks assembly
Check the Ladder installation as per manufacturer…