Thursday 8 - 18 February 2024
Khun Moo is upcountry and won't be coming in to work.
0 notes
Text
Day 36 - Wednesday 7 February 2024
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Day 35 - Tuesday 6 February 2024
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Day 34 - Monday 5 February 2024
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Sunday 4 February 2024
Khun Moo did not come in to work.
0 notes
Text
Saturday 3 February 2024
Khun Moo did not come into work today.
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Day 33 - Friday 2 February 2024
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Day 32 - Thursday 1 February 2024
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Day 31 - Wednesday 31 January 2024
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Day 30 - Tuesday 30 January 2024
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Day 29 - Monday 29 January 2024
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
❣️ Tuesday 23 - Thursday 25 January 2024 I was in Jakarta for FITFWT Jakarta.
❣️Friday 26 - Sunday 28 January 2024 Khun Moo was sick and could not come to work.
0 notes
Text
Day 28 - Monday 22 January 2024
Kitchen counter has been put in place, but needs to be cut to insert the stove and sink.
Outside walls continue to be touched up and sandpapered.
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Day 27 - Sunday 21 January 2024
Painting the kitchen door, and outside front door and window the Shakespeare Blue.
Fixing the holes and sandpapering where the air conditioning unit and wiring use to be for upstairs.
Neigbours at the back cut their trees.
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Day 26 - Saturday 20 January 2024
Fixing the holes and sandpapering where the air conditioning unit and wiring use to be.
Blocking the gap in the kitchen.
Continuing to paint the outside ceiling.
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes
Text
Day 25 - Friday 19 January 2024
No one came to work today, but Khun Moo came to drop off the white tiles for the kitchen.
Tumblr media
0 notes
Text
Day 24 - Thursday 18 January 2024
The outside of the hood exit installed.
Khun Moo started measuring out the kitchen counter stone. He also bought the solar powered lights and large outside spotlight. Continued with trimming for kitchen and foundation for cabinets around the feet.
(2 of his workers didn't come to work)
Tumblr media Tumblr media Tumblr media Tumblr media Tumblr media
0 notes