Update 07.03.19
It was great to see the crisp new Amiri logo featured throughout the Brecknock site. Ben and Chris now also have it proudly displayed on their hard hats!
1 note
·
View note
Update 10.01.19
Our Countess of Brecknock site is quite a complicated build as it connects to the existing building which is on a different level. The construction requires a large retaining wall which is already at an advanced stage. The retaining wall includes extensive drainage and moisture defence properties to ensure water cannot seep through to the new basement from the higher level.
One of the defences is the RIW Cavity Drain R20 membrane drainage system. The HDPE profiled sheet has 20mm raised turrets which channel any water ingress to a sump or collection point for safe disposal.
1 note
·
View note
Update 12.12.18
The Blogging Team were delighted to visit our Countess of Brocknock site on the first day the new building began to rise from the ground.
See below for full updates...
0 notes
Update 12.12.18
With groundwork’s continuing excess chalk is being removed by tractor and trailer. This allows for greater manoeuvrability and safety on a tight site with the public still accessing the hospital services.
0 notes
Update 01.11.18
Work at our Countess of Brecknock Hospice site was well under way when the Blogging team visited on the first of November.
See below for full updates...
1 note
·
View note
Update 01.11.18
The site is quite striking on first viewing due to the colour of the soil. As with much of the Andover area it is chalk based, with approximately 265 to 365 meters of Upper Cretaceous Chalk underlying the district. This forms the extensive dip slopes and undulating ground seen throughout Andover. See the Technical Focus on chalk below for more information.
The chalk soil can actually help work at the early stages of the build. If it stays dry it can allow for cleaner lines in the foundation digging and the trench walls are also less prone to collapse. On the site the foundations to the lower level have commenced and the main split level retaining wall is well underway.
Demolition of the existing structure has started and the balcony will be removed over the coming week. Later in November work on the substructure block work and drainage will begin.
1 note
·
View note
Update 01.11.18
On all Amiri sites the health and safety of our own workers and also the nearby community is of paramount importance. As we know construction work can be disruptive (particularly in the winter months), so all lorry deliveries at the Countess of Brecknock Hospice get the hosepipe treatment to wash the chalk and debris off the wheels before heading back into the surrounding community.
1 note
·
View note