OPS 571 Week 4 Quiz/OPS 571 Week 4 Quiz
1. A work breakdown structure isa hierarchy of tasks, subtasks, and work packagesa Cost and Performance tracking schedulea structure that is incompatible with the Critical Path Methoda simple list of the activities making up a project2. The vertical axis on a Gantt chart is usually which of the following?ActivitiesTimeCostProfit3. Which of the following identifies a […]
The post OPS 571 Week 4 Quiz/OPS 571 Week 4 Quiz appeared first on Novelty Essays.
0 notes
new-ops-571-blog · 8 years
Link
OPS 571 Week 4 Quiz
To purchase this material click below link
http://www.assignmentcloud.com/OPS-571/OPS-571-Week-4-Quiz
 For more classes visit
www.assignmentcloud.com
1.) A work breakdown structure is
a hierarchy of tasks, subtasks, and work packages
a Cost and Performance tracking schedule
a structure that is incompatible with the Critical Path Method
a simple list of the activities making up a project
 2.) The vertical axis on a Gantt chart is usually which of the following?
Activities
Time
Cost
Profit
0 notes
uopnewops571-blog · 8 years
Link
1.) A work breakdown structure is
a hierarchy of tasks, subtasks, and work packages
a Cost and Performance tracking schedule
a structure that is incompatible with the Critical Path Method
a simple list of the activities making up a project
2.) The vertical axis on a Gantt chart is usually which of the following?
Activities
Time
Cost
Profit
3.) Which of the following identifies a key principle of Reengineering?
Organize around tasks.
Downsize (lay-off) workers and do the same amount of work as before.
Merge information-processing work into the real work that produces the information.
Capture information both at the source and where it is interpreted.
4.) At the onset, a project originates as which of the following?
A Gantt chart
A series of milestones
Critical path method (CPM)
A statement of work (SOW
5.) Consulting firms typically use which of the following techniques to plan and monitor the engagements of the firm or specific projects?
CPM/PERT
Qualitative forecasting
Materials requirements planning (MRP)
Quantitative layout
6.) A Responsibility Chart specifically identifies which of the following?
Planning the tasks for a project
Customer satisfaction
Commitment to quality
Level of inventory
7.)Which of the following would be the result of subdividing a project?
Job orders
Work events
Job categories
0 notes